Saturday, November 1, 2014

Test Dev on Double Take 5.2

My prep for initial test development in my homelab was to create at least two (2) identical servers S2008-A and S2008-B, to install Double Take  5.2 on both. At the moment, I'm planning to to simulate the features of High Availability and DT-Move and as well to practice on P2V & V2V migrate and conversion excercises.

Server installation on esxi for initial prep...
Double Take installation...

Replication Console... S2008A is the target server, S2008B is the Source server to replicate on S2008A server.

...got an error setting up, IPaddress of Source and Target must be properly set.

I got it worked after proper IP configuration was set. Mirroring is now running, it should replicate after mirroring is done from the local set replication folder.


A little view from my Workstation10... waiting for Mirroring to complete.



...to be continued. Test dev in progress...